  • Ventspils Wind

    Ventspils Wind

    Ventspils Wind

    One of the first utility scale Wind parks in Latvia. With 10 wind turbines, the park will have a utility-scale capacity of approx. 66 MW.

    Milestones and timeline

    • 2020: Development permit from Ministry of Economy
    • 2022: EIA approved
    • 2022: Local plan approved
    • 2023: Ready-to-build of substation
    • 2024: Construction of substation
    • 2025, Q1: Ready-to-build and construction of wind park
    • 2025: Planned construction of wind park
    • 2026: Planned substation commissioning
    • 2026-2027: Planned wind park commissioning – Start of energy production